|
2009 – LIEN LAWS
In dealing with the
lien laws, the
primary focus for
the courts during
2009 was the
distinctions between
commercial and
residential
projects. The US
District Court
affirmed the earlier
decision of the
Bankruptcy Court
that subcontractor
work on a large
residential project
was subject to the
residential lien
requirements;
latitude was given
on the lien
arbitration
processes; and in a
currently unreported
decision involving
fall-out issues from
the Kara Homes
bankruptcy, the
court required
allocation of lien
sums to individual
residential units.
In the commercial
area, the court
placed strict
requirements on the
ability to pursue a
landlord’s
interests.
Relaxing Procedures
in Residential
Arbitration
Schadrack v. K.P.
Burke Builder, LLC
(407 N.J. Super.
153, App. Div.
2009)
In this
residential
construction case,
both the prime
contractor and its
subcontractor filed
Notices of Unpaid
Balances (“NUB”) but
only the
subcontractor filed
and served the
demand for
arbitration as
required by the
Construction Lien
Law (“CCL”). The
lien arbitrator
thereafter entered
an award in favor of
the subcontractor
allowing it to file
a lien for
approximately
$39,000, which was
then done. The
contractor filed an
amended NUB with the
arbitration demand
and received an
award allowing the
filing of a lien for
approximately 25% of
the amount claimed
in the amended NUB
and demand. In each
instance the lien
was ultimately filed
within the 90 day
time period. The
owner attacked the
sub’s liens based
upon a claim that
the sub did not
initially provide
the arbitrator with
all supporting
documentation
(although a
supplemental
submittal was made)
and the sub did not
use the contractor’s
full corporate name.
The trial court
rejected the owners’
claims for dismissal
of the liens.
The
Appellate Division
affirmed. The court
found that in
general the
residential
procedures are to be
strictly met.
However, in the
subcontractor
situation, failure
of the sub to
include all
documentation in
support of its
position with the
initial arbitration
demand and failure
to identify its
customer (the prime
contractor) by the
full corporate name
were not fatal
deficiencies. With
regard to the prime
contractor’s claims,
while the
arbitration demand
is required to be
filed and served
with the NUB, the
court applied the
requirement for a
showing of “material
prejudice”, which
was not demonstrated
by the owners. The
court also rejected
the owners’ argument
that the award
should be rejected
on the basis that
the award was issued
more than 30 days
after the initial
NUB. The court
found that it was
still within 30 days
of the amended NUB
and followed 2 days
of hearings. The
court further held
that the 30 day
limitation would not
be read so rigidly
as to eliminate the
ability of the
American Arbitration
Association to,
within reason, work
with its
scheduling.
Residential
Requirements Apply
to Subcontractor
Work on Subdivision
Michael J. Wright
Construction Co. v.
Kara Homes Inc.
(396 B.R. 131, US
District Court,
District of NJ,
2008)
Affirming the
Bankruptcy Court,
the US District
Court found that
under the NJ
Construction Lien
Law (“CCL”), a
subcontract
agreement to perform
framing for a
developer for
hundreds of dwelling
units constituted
“residential
construction”,
subjecting the lien
claimant to the
residential
provisions of the
CLL. The argument
of the
contractor/claimant
that since the CLL
spoke of single or
two-family dwelling
in its definition of
“residential”, it
would not be subject
to the added
residential lien
requirements in a
large development
was rejected.
Claimant Forced to
Allocate Sums due
Among Properties
Hirsch v. H&D
Prime Construction,
Inc. (App. Div.
April 2009)
In this
residential
construction dispute
arising out of the
Kara Homes
bankruptcy, the
defendant (a
subcontractor on a
development) filed a
NUB on the last 2
properties held by
the developer. The
Plaintiff homeowner
bought from the
developer while
aware of the NUB and
following the
service of the NUB
and demand for
arbitration.
Thereafter, the
arbitrator granted
an award to the sub
for over $146,000
and the lien was
filed. Plaintiff
sought a court
determination to
establish the
proportionate value
of the services to
her home, seeking to
develop an
allocation by lot.
The trial court
rejected plaintiff’s
position. The
Appellate Division
reversed, finding
that there must be
an allocation
between lots where a
multiple residential
project is involved,
and remanded to the
trial level to take
proofs on the value
of the goods and
services provided to
plaintiff’s lot.
Landlord Must
Approve the
Contract
The Benmoore
Construction Group,
Inc. v. Herod
Rutherford
Developers, LLC
(App. Div., Nov.
2009) Unpublished
In a
case where the
contractor for the
tenant pressed
unjust enrichment
and lien claims
against the
landlord, the court
repeated existing
case law that
prevents such claims
for unjust
enrichment, finding
that the
contractor’s only
ability to jump past
the party with whom
it contracted was
the lien law. The
court then
determined that in
the absence of a
specific writing
where the landlord
approved the
specific contract
(not just the work
or project) between
the tenant and
contractor, the
contractor had no
lien rights. Here
the plans for
renovation, but not
the contract itself,
were attached to the
lease and were
approved by the
landlord,.
CURETON
CLARK, P.C.
James H. Landgraf, Esq.
|